Cleansing, test migration, reconciliation and cutover steps for moving customers, stock and balances.
More than half of ERP projects are delayed by data quality. Moving junk data to a new system just speeds up the junk. Below is a six-week migration plan for a mid-sized company.
Week 1: Scope and inventory
Decide which data will move: open items, current balances, active item cards. Detailed movements for closed years are usually not migrated; they are kept as archive reports.
Week 2: Data cleansing
- Merge duplicate customer cards (same tax number, different spelling).
- Complete missing tax numbers, addresses and phone numbers.
- Deactivate unused item cards and standardise units and barcodes.
Week 3: Template mapping and first test migration
Old-system columns are mapped to Düzlem templates. The first migration to the test environment is made; trial balance and stock value are compared with the old system. A list of expected differences is kept.
Week 4: Reconciliation and fixes
Customer balances, open invoices, cheque/note portfolio and stock quantities are verified line by line. Sources of difference (rounding, exchange rate, period cut-off) are documented.
Week 5: User acceptance testing and training
Super users test their own scenarios: order, waybill, invoice, collection, month-end close. Training is completed.
Week 6: Cutover
A month-end or period-end cut-off date is chosen. Final balances are migrated and the old system is made read-only. Intensive support (hypercare) is planned for the first two weeks. A rollback plan is kept ready.
Success criteria
- Trial balance equals the old system to the last kuruş
- Stock value difference below 0.5%
- First month-end close shorter than five working days
You can download our migration templates from the documentation section and arrange a free migration analysis call with our implementation consultant.
Common mistakes
- Migrating without cleansing: the same customer stays on four different cards and reports mislead.
- Moving balances but forgetting open items; collection tracking becomes difficult from the start.
- Running the test migration only once; at least two rounds are needed.
- Scheduling go-live mid-month, which makes reconciliation harder.
- Going live without training users.
Assigning a data owner (usually the chief accountant) to the project team prevents half of the errors.